• 6D At-Risk Analysis
At-Risk · Power Grid Capacity Markets · Reliability Shortfall

The Auction That Keeps Coming Up Short: Two Shortfalls, Worse the Second Time

PJM Interconnection's capacity market exists to guarantee enough generation is under contract to keep the lights on. Its own \" 2027/2028 Base Residual Auction Reserve Target Shortfall Report,\" dated February 9, 2026, disclosed a shortfall of 6,517 MW of unforced capacity against the reliability requirement — an installed reserve margin of 14.4% against a 20% target, the first time in the capacity market's history the full RTO missed its target.[1] Five months later, PJM's own July 14, 2026 release confirmed the following auction, for the 2028/2029 delivery year, came in short again: 6,831 MW below target, a 14.7% margin — a second consecutive shortfall, and a larger one in absolute terms.[2] This isn't a single bad auction. It's a market mechanism specifically designed to guarantee reliability missing its own target twice in a row, with the gap widening rather than closing. This case documents the shortfall as PJM itself disclosed it — not a projection or an outside estimate.

6,517 MW
First shortfall, 2027/2028 auction
6,831 MW
Second shortfall, 2028/2029 auction
14.4%
First reserve margin, vs 20% target
14.7%
Second reserve margin, still short
1st ever
Full-RTO miss in market history
2
Consecutive auctions missing target

6D Foraging Methodology™

01

The Insight

PJM's capacity market runs an annual Base Residual Auction three years ahead of delivery, designed to lock in enough generation to meet a 20% installed reserve margin above expected peak demand — a buffer specifically sized to keep the grid reliable even under stress. PJM's own February 9, 2026 report on the 2027/2028 delivery year disclosed the auction cleared at a 14.4% installed reserve margin — 6,517 MW of unforced capacity short of the 20% target.[1] PJM's own characterization: the first time the full RTO has missed its reliability target since the capacity market began.

The obvious question after a first-ever miss is whether it was a one-time event or the start of a trend. PJM's own July 14, 2026 release answers it: the next auction, for the 2028/2029 delivery year, cleared at a 14.7% margin — 6,831 MW short of target.[2] The percentage margin improved marginally (14.4% to 14.7%), but the absolute shortfall grew (6,517 MW to 6,831 MW), because the reliability requirement itself grows as expected peak demand rises. Two consecutive auctions, two consecutive misses, a larger absolute gap the second time.

PJM's own communications don't attribute the shortfall to a single cause, and this case doesn't either — generator retirements, interconnection-queue delays for new supply, and rising demand (data centers among several drivers, not the only one) all contribute. What's confirmed and precise is the outcome: a capacity market purpose-built to guarantee a reliability margin has now missed that margin twice running, with PJM's own numbers showing the gap growing in absolute terms.

The honest limit of this case: a capacity shortfall is a market signal, not an automatic blackout — PJM has other tools (including the emergency generation orders documented in this cluster's diagnostic case) to manage reliability even with a capacity margin below target. What this case supports precisely is that the structural cushion the market is designed to guarantee has now failed to materialize twice in a row, and the response tools being used to cover the gap are, on the evidence in this cluster, becoming more frequent rather than less.

6,517 → 6,831 MW
PJM's own disclosed capacity shortfall, first auction to the next

Two consecutive capacity auctions, two consecutive misses against PJM's own reliability target, a larger absolute shortfall the second time.[1][2]

02

The Timeline

How a first-ever capacity-market shortfall became a two-auction pattern within five months.

Feb 9, 2026

The first-ever shortfall

PJM's own report discloses the 2027/2028 Base Residual Auction cleared 6,517 MW short of the reliability target — the first full-RTO miss in the capacity market's history.[1]

First Miss
Jun 18, 2026

FERC issues show-cause orders

FERC orders PJM and five other RTOs to justify their large-load interconnection tariffs, with a response deadline in mid-August — a regulatory response to the pattern this case documents.[3]

Regulatory Response
Jul 14, 2026

The second shortfall confirms a trend

PJM's release shows the 2028/2029 auction cleared 6,831 MW short — a larger absolute gap than the first miss, five months later.[2]

Second Miss
Sep 2026

PJM seeks a special backstop procurement

PJM's own July release confirms it will seek FERC approval for a special backstop procurement — a direct response to the consecutive shortfalls.[2]

The Response
Dec 2026

The next auction

The 2029/2030 delivery year Base Residual Auction is scheduled — a third consecutive shortfall would be a major structural confirmation.[2]

Next Test

The first time the full RTO has missed its reliability requirement. — PJM Interconnection, 2027/2028 Base Residual Auction Reserve Target Shortfall Report, February 9, 2026

DimensionEvidence
Revenue (D2) Origin · 86 The lever is a capacity-market mechanism — a financial structure specifically designed to guarantee a reliability margin — missing its own target twice consecutively, on its own disclosed numbers.[1][2] D2 is the origin because this entire case is about a market outcome, not a physical event.The Market Missed Its Target
Operational (D6) L1 · 78 A widening capacity shortfall directly increases reliance on the emergency generation mechanism documented in this cluster's diagnostic case — a real operational consequence of the market missing its target.[1][2] D6 amplifies from D2 as the physical consequence of the financial shortfall.More Frequent Emergency Reliance
Regulatory (D4) L1 · 74 FERC's June 2026 show-cause orders to PJM and five other RTOs on large-load interconnection tariffs are a direct regulatory response to the pattern this case documents.[3] D4 amplifies alongside D6 as the institutional response to the shortfall.FERC's Own Scrutiny
Customer (D1) L2 · 60 Every customer on the PJM grid is exposed to whatever reliability or price consequence follows from a capacity market missing its own target twice — the population this case's outcome ultimately touches.[1][2] D1 sits here as that broad exposed population.
Quality (D5) L2 · 52 The honest distinction between a capacity-market signal and an imminent reliability failure is the discipline keeping this case precise rather than alarmist — PJM has other tools even with a shortfall on the books.[1][2] D5 sits here as that boundary.
Employee (D3) 30 Deliberately the thinnest dimension. This is a capacity-market and grid-infrastructure cascade; no comparable workforce-level finding exists in the research.
03

6D Cascade Analysis

The cascade originates in D2 — Revenue — because the lever is a capacity-market mechanism, a financial structure designed to price and guarantee reliability, missing its own target on its own numbers.[1][2] From D2 it amplifies into D6 (the operational consequence — more frequent reliance on emergency generation tools) and D4 (the regulatory response — FERC's own scrutiny of the large-load interconnection process feeding this shortfall).[3] It then reaches D1 (every customer on the PJM grid, exposed to whatever reliability or price consequence follows) and D5 (the honest distinction between a market signal and an imminent reliability failure). D3 is deliberately thin — a capacity-market and grid-infrastructure cascade, not a workforce one. Cross-references: [UC-285] documents the emergency-generation mechanism increasingly covering this shortfall; [UC-287] shows one major demand source removing itself from the market this shortfall describes; [UC-288] scoreboards whether the next auction narrows or widens the gap further.

FETCH Score Breakdown

Chirp: 82
|DRIFT|: 43
Confidence: 0.81
FETCH = 82 × 43 × 0.81 = 2,692  →  MONITOR — SHORTFALL WIDENING (threshold: 1,000)
Calibration: FETCH 2,692 reflects strong primary sourcing — both shortfall figures come directly from PJM's own published reports, not third-party estimates. DRIFT 43: methodology strong (two consecutive, PJM-disclosed auction results, directly comparable) against performance genuinely at risk — a first-ever miss followed by a larger absolute miss is a real, structural trend, not noise. Confidence 0.81 reflects high certainty in the reported figures; the open question is whether a third consecutive auction extends the pattern.
5 of 6
Dimensions Hit
Missed, then worse
Multiplier
2,692
FETCH Score
Origin D2 Revenue
L1 D6 Operational+ D4 Regulatory
L2 D1 Customer+ D5 Quality
L3 D3 Employee
CAL Source auction-keeps-coming-up-short · at-risk · D2 origin · PJM capacity market missed reliability target 2 consecutive auctions, shortfall widening auction-keeps-coming-up-short.cal
-- UC-286: The Auction That Keeps Coming Up Short: 6D At-Risk Cascade
-- PJM capacity market missed reliability target 2 consecutive auctions (6,517 MW then 6,831 MW short), gap widening (cluster: UC-285/287/288)
FORAGE auction_keeps_coming_up_short
WHERE first_shortfall_confirmed = true
  AND second_shortfall_confirmed = true
  AND absolute_gap_widened = true
ACROSS D2, D6, D4, D1, D5, D3
DEPTH 3
SURFACE auction_keeps_coming_up_short

DIVE INTO one_time_versus_trend
WHEN first_auction_misses_target = true
  AND second_auction_misses_by_more = true
TRACE capacity_shortfall_cascade
EMIT reliability_margin_signal

WATCH third_consecutive_auction WHEN december_2026_bra_results_confirm_or_break_trend = true

DRIFT auction_keeps_coming_up_short
METHODOLOGY 86
PERFORMANCE 40

FETCH auction_keeps_coming_up_short
THRESHOLD 1000
ON MONITOR CHIRP high 'PJM's own Feb 9 2026 report: 2027/2028 Base Residual Auction cleared 14.4pct IRM vs 20pct target, 6,517 MW UCAP short - first-ever full-RTO shortfall in the capacity market's history. PJM's Jul 14 2026 release: 2028/2029 auction cleared 14.7pct IRM, 6,831 MW short - percentage margin improved slightly but absolute shortfall grew. Two consecutive misses, gap widening in absolute terms'

SURFACE analysis AS json
SENSE FORAGE: PJM's '2027/2028 Base Residual Auction Reserve Target Shortfall Report' (Feb 9 2026, PJM primary source): 14.4pct installed reserve margin vs 20pct target, 6,517 MW UCAP short - first-ever full-RTO shortfall in the capacity market's history. PJM's Jul 14 2026 press release: next auction (2028/2029 delivery year) cleared 14.7pct IRM, 6,831 MW short - percentage margin improved marginally but absolute shortfall grew because the reliability requirement itself rises with expected peak demand. Not attributed to a single cause by PJM - generator retirements, interconnection-queue delays, rising demand (data centers among several drivers) all contribute. Signal: a capacity market designed to guarantee a reliability margin has missed its own target twice consecutively, gap widening in absolute terms.
ANALYZE DRIFT 43 - methodology strong (86: both shortfall figures are PJM's own disclosed, directly comparable auction results, not third-party estimates) against performance genuinely at risk (40: a first-ever miss followed by a larger absolute miss is a real structural trend). D2 origin (a capacity-market mechanism missing its own reliability-guarantee target) cascades to D6 (more frequent emergency-generation reliance) + D4 (FERC's own scrutiny of the interconnection process feeding this), then D1 (every PJM customer exposed) + D5 (market signal vs imminent failure, the honest distinction). D3 thin - capacity-market/grid-infrastructure cascade, not workforce.
DECIDE FETCH 2,692. MONITOR - SHORTFALL WIDENING: both shortfall figures are confirmed, primary-sourced, and directly comparable across two consecutive auctions - not an inference from a single data point. Confidence 0.81 reflects strong certainty in the reported figures. WATCH: whether the December 2026 Base Residual Auction (2029/2030 delivery year) extends the pattern to a third consecutive miss, and whether UC-285's emergency-generation mechanism keeps covering the gap in the meantime.
04

Key Insights

The percentage margin barely moved. The absolute gap got worse

14.4% to 14.7% reads like modest improvement. 6,517 MW to 6,831 MW short is the more honest number — the reliability requirement itself grows with demand, so a flat percentage still means a bigger real-world hole.[1][2]

PJM disclosed both numbers itself

This case isn't built on an outside estimate or advocacy framing — both shortfall figures come from PJM's own published reports about its own market's performance.[1][2]

A capacity shortfall isn't the same as a blackout

PJM has other reliability tools, including the emergency generation orders this cluster's diagnostic case documents — the shortfall is a market-design failure to hit its own target, not an imminent failure of the grid itself.

December's auction is the real test

Two consecutive misses could still be a two-auction anomaly. A third consecutive shortfall in December 2026 would be much harder to read as anything but a structural trend.

Sources

Three sources: PJM's own two shortfall reports for consecutive Base Residual Auctions, and FERC's June 2026 show-cause orders on large-load interconnection tariffs, the regulatory backdrop feeding into the shortfall.

Tier 1 — Official & Structural Data
[1]
PJM Interconnection, \" 2027/2028 Base Residual Auction Reserve Target Shortfall Report\" (Feb 9, 2026): 14.4% installed reserve margin against a 20% target, 6,517 MW UCAP shortfall — the first time the full RTO has missed the capacity market's reliability requirement.pjm.com · Feb 2026
[2]
PJM Interconnection press release (Jul 14, 2026): 2028/2029 Base Residual Auction cleared at 14.7% installed reserve margin, 6,831 MW short of target; confirms PJM will seek FERC approval for a special backstop procurement in September 2026 and that the next Base Residual Auction (2029/2030 delivery year) is scheduled for December 2026.pjm.com · Jul 2026
[3]
FERC show-cause orders, issued June 18, 2026, to PJM and five other RTOs regarding large-load interconnection tariffs, with a 60-day response deadline (~August 17, 2026) and a 30-day mandatory reliability report.ferc.gov · Jun 2026

A capacity market built to guarantee reliability just missed its own target twice in a row.

The percentage margin barely moved. The absolute gap got bigger. PJM's own numbers, both auctions.